When a building project reaches the framing stage, abstract architectural drawings transform into physical, three-dimensional spatial reality. For the Architect of record, the framing field review is one of the most critical site visits in the construction administration phase (or Contract Administration (CA) Phase).

As the Architect and Coordinating Registered Professional (CRP), our primary objective during this review is to determine whether the framing layout and assembly details are in general conformance with the contract documents and the British Columbia Building Code (BCBC).

Whether you are an intern architect preparing for your first solo site visit or a seasoned practitioner refining your site review protocol, here is a general guideline of how to conduct an efficient, thorough framing field review.


1. Timing and Combining Field Reviews

Efficiency on-site starts with smart scheduling. A framing review rarely happens in complete isolation. Depending on the project’s construction sequencing and schedule, you can often coordinate or combine your framing field review with other complementary reviews:

  • Slab-on-Grade (SOG) / Foundation Reviews: Verifying anchor placement, grid lines, and slab depressions before or alongside framing layout.
  • Early Fire-Stopping / Penetration Reviews: Catching service penetrations through rated assemblies before walls are closed up with drywall or insulation.

Combining complementary reviews ensures you catch multi-trade interface issues early—before critical framing elements are concealed.


2. The Architectural Framing Checklist: What to Look For

While structural engineers focus primarily on gravity loads, shear walls, hold-downs, and structural connections, the architect’s lens focuses on spatial accuracy, fire safety, building envelope readiness, and life safety geometry.

Here are key items every AIBC field review should cover during framing:

Wall Types and Chase Dimensions

  • Plumbing and Utility Walls: Ensure designated 6” (2×6) or larger stud walls are installed where major plumbing stacks, drainage, or HVAC ducts drop. Standard 2×4 wall cavities are easily overwhelmed by 3” or 4” soil pipes, leading to structural notch damage or dry-wall bulging if missed.
  • Partition Layouts: Verify overall room dimensions, rough openings (ROs) for doors, and wall thicknesses against floor plans.

Framing Details & Services

  • Architectural and Structural Details: Confirm double top plates are installed with proper overlapping corners and tie-plates where indicated on architectural and structural details. Ensure splices in top plates are offset by at least 4′(1.2m) from underlying studs or adjacent plate joints to maintain structural wall continuity and lateral diaphragm load transfer. Where top plates are notched or cut to accommodate vertical mechanical chases, verify that engineered metal tie-plates, steel straps, or top-plate brackets are installed to restore diaphragm tie capacity and keep wall intersections rigid.
  • Rough-Ins for Services: Check that framing around electrical, mechanical, and plumbing rough-ins leaves adequate clearance without compromising structural studs or fire separations. Confirm trades have not over-drilled load-bearing studs or notched joist flanges beyond BCBC code limits to fit piping and electrical runs. Where larger ductwork, main drainage stacks, or multi-conduit bundles pass through framing, verify that proper framed box-outs, double trimmers, and structural headers are built into the wall assembly. Additionally, ensure sufficient physical space is maintained around all rough-in penetrations within fire-rated assemblies so fire-stopping devices, intumescent sealants, and draft-stopping material can be fully installed without obstruction or overcrowding.

Life Safety and Fire Protection

  • Fire-Blocking in Concealed Spaces: Verify that fire-blocking is achieved in concealed spaces—such as stud cavity drop ceilings, soffits, and floor/ceiling transitions—to prevent the spread of flame and hot gases within hidden voids.
  • Fire-Stopping and Rated Assemblies: Check fire-stopping pre-configurations at fire compartments, demising walls, and rated shaft enclosures.
  • Continuity of Fire Separations: this is the best time to review the compliance with BCBC 3.1.8.3. Continuity of Fire Separations, this is an interesting topic which need a blog by itself, in general, you need to determine if the rim board at the fire compartment boundaries has a CAN/ULC listing or the GC has to protect it with GWB.

Circulation and Egress

  • Stair Geometry: Measure rough stair risers and treads across the entire run. Ensure rise and run dimensions comply with BCBC limits, accounting for future floor finish thicknesses (e.g., hardwood, tile, carpet) so the finished stairs maintain uniform riser heights.
  • Exit Widths: Measure clear framing widths along exit corridors, stair landings, and door rough openings to ensure required minimum egress widths are maintained.

Building Envelope Readiness

  • Vapour Barrier Pre-Strapping: Ensure vapour barrier membranes or air-barrier transition strips are pre-installed behind interior partition intersections, exterior wall connections, and ceiling transitions before framing is closed in.

3. The CRP Role: Cross-Consultant Coordination

As the Coordinating Registered Professional (CRP) under the AIBC framework and Letters of Assurance process, your duty extends beyond architectural site observations. You are responsible for coordinating both the design and the field reviews of all sub-consultants.

  • Verify Structural Engineer Reports: Confirm that the Structural Registered Professional (SREF) has conducted their required framing review and issued an official field report.
  • Cross-Disciplinary Concerns: If you spot something framing-related that raises structural concerns—such as an over-notched joist, missing hold-down, or unapproved header alteration—it is essential to document the concern in your architectural report and refer it immediately to the Structural Engineer (or relevant consultant) for their review and explicit comment.

4. On-Site Collaboration: The Value of Communication

A field review should never feel like an adversarial audit. One of the best practices during any site visit is to maintain an open dialogue with the Site Supervisor.

If you discover a layout deviation or framing conflict on site:

  1. Ask before assuming: Point out the issue to the site supervisor on the spot.
  2. Listen to site context: Supervisors often have valid context—perhaps an RFI response, a structural change directive, or an unforeseen site conflict prompted the modification.
  3. Collaborate on solutions: Discussing the issue on-site often leads to immediate, practical solutions that can be formally confirmed in the field report.

5. Wrapping Up: Back to the Office and Issuing the Report

After completing your walk, return to the office to promptly write and distribute your Architectural Field Review Report (FRR).

A clear framing field review report should always include:

  1. Site Progress Overview: Document the current stage of framing and overall construction progress, supported by dated site photographs.
  2. Consultant Referrals / Action Items: Clearly highlight concerns that require input, comment, or review from specific sub-consultants (e.g., structural, mechanical, electrical, or acoustic).
  3. Deficiencies Requiring Correction: List specific non-conforming items that the general contractor must rectify, referencing drawing numbers or detail tags where applicable.

Final Thoughts

The framing stage is the last practical opportunity to correct layout, structural interfaces, and life-safety detailing before walls are permanently closed up. By approaching framing reviews with a systematic checklist, active cross-consultant coordination as CRP, and collaborative site communication, Architects can safeguard both design intent and building performance.


Disclaimer

The information presented in this blog is for general educational and informational purposes only. It is designed to provide an overview of architectural field reviews. This content is not exhaustive and should not be considered professional architectural advice, specific design guidance, or a substitute for expert consultation. Building codes, regulations, and construction techniques are subject to change and specific interpretation based on project conditions. Glory Architecture Inc., its principals, and affiliates shall not be held liable for any decisions, actions, or omissions made in reliance on the information contained within this blog. Always seek the advice of a competent, licensed professional for your individual project needs.